during a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. you can therefore conclude that:
once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. this will provide information on the ( ) and identification of the ( ) .
which type of process involves the agency holding discussions with each of the offerors, after receipt of their proposals, in the process of arriving at an agreement prior to the award of a contract?
an element in the wbs was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50k. the task was completed in 1000 hours but a burdened cost of $60k. the most likely reason for the increase would be:
the type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. for a firm fixed price contract, payment for risk ( ) .
a network has been developed with resources from six different departments. one of the six departments has just informed you that they can increase the number of employees from 5 to 8. this will result in:
conflict management requires problem-solving. which of the following is often referred to as a problem-solving technique and used extensively in conflict resolution?
management has decided to "crash" a project in order to avoid penalty payments for late deliveries. to crash the project, either overtime or additional resources should be assigned to: